Pause HS2 reset until you are confident it can be delivered, NAO tells ministers

An artist's impression of a white HS2 high-speed train with blue accents travels along tracks with overhead power lines
HS2 is now expected to cost up to £102.7bn, with trains not running until as late as 2039 – £70bn more and 13 years later than originally promised. Photograph: HS2/PA

Revised plans for HS2 should not be put into action until the government is confident they can be delivered, according to the public spending watchdog.

The project to build the high-speed railway must be put on a stable footing to avoid a repeat of past failures, the National Audit Office (NAO) said in a report.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.