Boiler light-up of two Yadadri Thermal Power Station units sets in motion its phased commissioning

In a significant development, the engineers of Telangana State Power Generation Corporation (TS-Genco) have taken up boiler light up and auxiliary boiler light-up of Unit-I and II of the 5×800 megawatt Yadadri Thermal Power Station (YTPS) near Veerlapalem in Damaracharla mandal of Nalgonda district on Tuesday.

The boiler light up will set in motion the process of commencement of power generation in the plant first on an experimental basis and later on a commercial basis. As per the revised environmental clearance granted to the project in April first week, the first two units are scheduled to be commissioned on October 15 this year.

The EC given to the project in June 2017 was suspended by the National Green Tribunal (NGT) in September 2022 following the change in utilisation of coal from the initial blend of 50% each imported and indigenous coal to 100% indigenous coal and a complaint lodged by an NGO on the change of use in coal and its impact on the local environment. The NGT had had ordered fresh public hearing and appraisal of the project proposal.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.