Vijayapura airport expected to be ready by February 2024

The State government told the Legislative Council on December 5 that the Vijayapura airport is expected to be ready by February 2024.

Replying to a question by Prakash K. Rathod, Minister for Small Scale Industries and Public Enterprises Sharanabasappa Darshanapur told the Council that the airport was being developed at a cost of ₹347.92 crore to enable the operation of Airbus 320 type aircraft. So far, ₹310 crore had been spent on the project.

Package I works, under progress since February 2021, had been completed to an extent of 91%. Package II works, launched in April 2022, had been completed up to 82% extent. Package III works, under progress since October 2022, had been completed up to 79%, he said.

The Minister said that 727.01 acres of land was acquired for the project. Of this, compensation of ₹31.92 crore had been disbursed for acquiring 351 acres. In addition, ₹2.25 crore had been deposited for 28.08 acres in court. Of the land acquired, 347.33 acres were government land, he said.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.