Get all your news in one place.
100's of premium titles.
One app.
Start reading
The Hindu
The Hindu
National
Staff Reporter

Second phase of pipe-laying work begins in Alappuzha

The second phase of replacing defective pipelines under the Alappuzha drinking water project has begun.

Officials of the Urban Infrastructure Development Scheme for Small and Medium Towns (UIDSSMT) said on Saturday that around 350 metres of pipeline would be laid at Thakazhi. "We hope to complete the second phase of pipe-laying work in 15 days. The ongoing work will not affect the pumping and water supply. In the next phase, some 450 metres will be laid. We hope to complete the entire work before the onset of monsoon," said a UIDSSMT official.

The work is being carried out by digging the Ambalapuzha-Thiruvalla road. The plan is to lay around 1,200 metres of 900-mm mild steel pipe at Kelamangalam and Thakazhi. In the first phase, 370 metres of pipeline had been laid at Kelamangalam.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.