The construction of the new Parliament building was 44% complete, while the redevelopment of the Central Vista Avenue, which hosted the Republic Day Parade, had achieved 80% of the physical targets, the Housing and Urban Affairs Ministry informed the Rajya Sabha on Monday.
In a written reply, Housing and Urban Affairs Minister of State Kaushal Kishore said ₹480 crore had been spent on the new Parliament building so far. The project has the deadline of October so that the Winter Session of Parliament is held in the new building.
The Central Vista Avenue project has so far cost ₹441 crore, with 80% of the work complete. Though portions of the project were pending, the Republic Day Parade was held on Rajpath.