After having spent ₹40.78 crore and completed construction of a multi-level car parking facility on D.B. Road, R.S. Puram, the Coimbatore Corporation finds itself in a spot where it is unable to throw open the space for use.
The Corporation sources said the civic body was awaiting power connection and to get to the power connection it needed the completion certificate from the Local Planning Authority.
To get the completion certificate, the civic body needed the planning permission, which it did not have.