Dominic D Ahiaga-Dagbui, Director of Deakin Megaprojects Research Group and Senior Lecturer of Construction and Project Management, Deakin University

Why Snowy Hydro’s $25 billion cost blowout is a warning sign for other megaprojects

Australia’s biggest renewable energy project, the “Snowy 2.0” hydro scheme in New South Wales, is now expected to cost up to A$25 billion – more than 12 times the original figure, an official new report has confirmed.

Snowy 2.0 also won’t be completed until late 2029. This is eight years after the initial projection announced by then-Prime Minister Malcolm Turnbull in 2017. Its anticipated price tag was just $2 billion then, though there was no business case to back that up at the time.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.