Uranium clean-up way over budget, running late… sounds like true nuclear power

Peter Dutton and the radioactive gang of nuclear spruikers in the media seem to think that if only they call for a “mature debate” long enough, small nuclear reactors (SMRs) will just pop into being.

But like any energy source, nuclear power comes with a host of practical challenges that don’t seem to feature in the op-eds and speeches about how SMRs are just around the corner.

Take, for example, the plight of Energy Resources of Australia (ERA) — the almost wholly owned subsidiary of Rio Tinto that operated the Ranger uranium mine in Kakadu in the Northern Territory from 1980 until 2021, when it was closed and rehabilitation work started.

The 2019 budget for the rehabilitation: $973 million.

In February 2022, as the inadequate nature of the planning and other work on cleaning up the mine became clear, ERA announced the cost would actually be a range of $1.6 to $2.2 billion. And the original finish date of 2028 would be missed, it said.

Wait, we can hear you saying — a nuclear power-related project that went over budget and over schedule? We’re shocked — shocked!

But hang on: ERA now says it expects total costs for the rehabilitation of the Ranger mine to, erm, “materially exceed” its previous estimate. “Materially” in this context means a large amount of money.

The company was supposed to have received a 2022 feasibility study by this month, which would “address the rehabilitation requirements on components where enough certainty can be obtained, including a revised estimated schedule and cost, through to September 2027”. That study will now arrive next month, when ERA will update the market and consult with stakeholders.

So what will the final bill be? The company is “unable to confirm the estimated complete project schedule and total rehabilitation costs at this time, due to a number of uncertainties including the outcome of the final 2022 feasibility study, the outcome of the additional studies and the further work to be undertaken by ERA to verify and attempt to mitigate estimated costs identified in those studies”.

This is the latest in a string of bad news for ERA: in its financial report for the half-year to June, the company revealed that the loss attributable to owners grew tenfold to $331.3 million from $33.6 million. The uranium producer’s revenue from continuing operations slumped to just $13.4 million from $47.7 million.

ERA said the loss in changes in the estimate of rehabilitation provision was $301.6 million for the half (that’s because the rehab cost estimate rose by $368 million in the six months to June, lifting the estimated cost of the work to $2.18 billion, meaning there is very little headroom available for further cost rises).

In April, ERA sought $369 million from shareholders in an issue to which Rio Tinto contributed $319 million. That helped the company’s cash position rise to $823 million at June 30, comprised of “$227 million in cash at bank, $100 million investments in term deposits with maturity dates greater than three months and $496 million of cash held by the Commonwealth government as part of the Ranger Rehabilitation Special Account (Trust Fund). The company has no debt and $125 million in bank guarantees”.

So ERA has cash to fund the rehabilitation, for now. But if the “material” increase in the cost is substantial, to whom will ERA turn? Taxpayers, perhaps?

Late, massively over budget, and reliant on taxpayer subsidies. Sounds like nuclear power to us — small and modular or not.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.