Unending ‘alignment issues’ bog connectivity projects in Mysuru

A slew of infrastructure works pertaining to road, air and rail in Mysuru have been impacted by alignment issues as a result of which the projects have been delayed, besides adding to cost escalation.

The airport expansion is bogged due to the alignment of the existing Mysuru-Nanjangud highway, and track alignment between the two skirts the airport runway at the other end. As a result the Directorate General of Civil Aviation and the Airport Authority of India have refused permission to draw the overhead power cables at a 100 metre stretch on the Mysuru-Nanjangud-Chamarajanagar section.

The fallout is that though the railways have completed the track electrification work on the entire Mysuru-Chamarajanagar section entailing a distance of nearly 60 km, the authorities are unable to operate electric locomotive hauled trains on the section due to the 100 metre gap near the airport.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.