Benita Kolovos Victorian state correspondent

Three stations ready, hospital dramas and more budget blowouts: is Melbourne’s Metro Tunnel still on track?

Politicians in rail tunnel
Former Victorian premier Daniel Andrews during a tour of the Arden Station rail development at North Melbourne, alongside then transport minister, Jacinta Allan. The project is currently scheduled to be completed some time in 2025. Photograph: Joel Carrett/AAP

The cost of the Victorian government’s Metro Tunnel rail project has blown out by an additional $837m.

At a snap press conference on Thursday afternoon, the state’s transport infrastructure minister, Danny Pearson, announced the government had reached a deal with the project’s builders to cover the growing construction costs of the new underground rail line.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.