The Southern Regional Power Committee (SRPC) has sought comments from other constituent States and the Union Territory in the region with regard to Tamil Nadu’s request for 100% allocation of power from Kudankulam Nuclear Power Plant (KKNPP) Units III and IV (1,000 MW each).
The commissioning of Unit III is expected to take place by May 2025, and that of Unit IV by December 2025, according to the additional agenda items included for the 193rd meeting of SRPC’s Operation Coordination Sub Committee, to be held on August 10.
SRPC cited a letter from the Union Ministry of Power (MoP), dated August 3, sent to the Central Electricity Authority in this regard.