Get all your news in one place.
100’s of premium titles.
One app.
Start reading
Insider UK
Insider UK
Politics
Neil Pooran & Peter A Walker

Sturgeon singled out for criticism in ferries fiasco report

A long-awaited report into the Ferguson Marine ferries fiasco has identified serious failings, including Nicola Sturgeon’s decision to prematurely announce the shipyard as preferred bidder.

Following months of investigation, a Holyrood committee found taxpayers and island communities have been “badly let down” by many of those involved in the project.

The 124-page report from the Public Audit Committee is the most comprehensive account so far of the troubled programme to build the Glen Sannox and the as-yet-unnamed Hull 802.

The ferries are meant to serve island communities in the west of Scotland, but are now five years late and with a price tag nearly tripled to almost £300m.

The decision to publicly announce Ferguson Marine Engineering - at that point owned by businessman Jim McColl - as the preferred bidder in 2015 came in for particular criticism.

Sturgeon personally attended the shipyard for the announcement, and the committee said the move “almost certainly” weakened the negotiating position of the ferry-owning body CMAL when problems emerged later.

One section of the cross-party committee’s report stated: “Given that it was clear that considerable negotiations were still required, we question the First Minister’s decision to publicly announce the preferred bidder.

“In light of the contradictory views on offer, further explanation should have been sought by ministers before the final decision was taken.

“The committee is not convinced that such a public announcement was necessary or indeed appropriate for this project, especially at that time, given the considerable work and negotiation that was required before CMAL could take a decision to award the formal contract.

“We believe that this almost certainly weakened CMAL’s negotiating position with FMEL, particularly as important details of the contract were still being worked out.

“It also remains unclear why the First Minister led on the preferred bidder announcement and why the First Minister’s press release and associated social media communications did not reflect that there were ‘significant negotiations to be concluded’.”

The two SNP members of the committee, Willie Coffey and Colin Beattie, did not support this part of the findings.

The committee’s report said the launch of the Glen Sannox in November 2017 - an event also attended by the First Minister - was premature.

Ministers were not aware of CMAL’s concerns about the launch but should have played a more active role, the report said.

Committee convener Richard Leonard said: “The people of Scotland have been badly let down by this project.

“There have been collective failures at government and agency level from the start.

“It has been dogged by a lack of transparency; by ineffective governance arrangements; by poor record keeping within the government; and by baffling communication failures.

“It is vital that lessons are learned, that means much-needed reform of governance arrangements for future vessel projects.

“But it also means a change in the way the government and its agencies conduct themselves and are accountable to parliament and the people.”

A number of recommendations are made by the committee, including greater transparency and record-keeping by the Scottish Government.

Other members of the government and public agencies also came in for criticism in the report.

The committee expressed “serious concern” at then infrastructure secretary Keith Brown’s failure to answer key questions about his role in the awarding of the contract.

It said former transport minister Derek Mackay showed “poor judgment” in sending an email to a constituency MSP, which Ferguson Marine interpreted as waiving its requirement to provide a builders refund guarantee.

The auditor general is still investigating the procurement process for the contract, following claims made in a BBC Disclosure documentary.

The committee was also frustrated by delays in receiving evidence from Transport Scotland officials, leaving them questioning the level of “respect” shown to parliamentary scrutiny.

Transport Scotland “consistently failed to accurately reflect CMAL’s significant concerns to Scottish ministers”, the MSPs said.

It is “particularly concerning”, they said, that no full record exists of a meeting between Sturgeon and McColl from May 2017.

The Scottish Government has produced an email discussing the contents of the meeting, but no full minutes.

It is still unclear how large amounts of public money were spent during McColl’s ownership of the yard, the report noted.

Don't miss the latest headlines with our twice-daily newsletter - sign up here for free.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.