Judge orders turbine manufacturer to stick with Massachusetts offshore wind farm project

Offshore Wind Lawsuit - (Copyright 2025 The Associated Press. All rights reserved)

A Massachusetts judge on Friday temporarily blocked a turbine manufacturer from pulling out of a major offshore wind farm project, saying it would be “fanciful” to imagine a new contractor could finish the installation.

Vineyard Wind went to court last week after GE Renewables said it would be terminating its contracts for turbine services and maintenance. GE Vernova, the parent company for GE Renewables, argued that Vineyard Wind owes it $300 million for work it performed, but Vineyard Wind countered that the manufacturer remains on the hook for about $545 million to make up for a catastrophic turbine blade collapse in July 2024 that set the project back by two years.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.