Exat drafts payout criteria for bridge in Koh Chang

Koh Chang residents listen as officials from the Expressway Authority of Thailand explain compensation criteria for landowners affected by the proposed bridge linking Trat mainland with the popular island. JAKKRIT WAEWKLAYHONG

TRAT: The Expressway Authority of Thailand (Exat) has outlined compensation criteria for landowners affected by the proposed Koh Chang bridge as residents raised concerns that payments may not be sufficient to help them relocate, despite broad support for the project.

The project timeline remains unchanged, with cabinet approval targeted for 2029, construction due to begin in 2031 and the bridge expected to open in 2035.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.