Could the M6 be Sydney’s unbuildable motorway due to sinkholes and a reverse fault?

Aerial photo showing roadworks continuing along President Avenue, Princes Highway and West Botany Street on M6 tunnel
The M6 motorway project is 90% completed but its fate remains up in the air as the CGU has said it will down tools due to the impact of a ‘complex faulting zone’. Photograph: Transport for NSW

A 245-metre section of a new Sydney motorway tunnel plagued by sinkholes and a “challenging” geological feature will bring a $3.1bn transport project to a grinding halt unless an 11th-hour deal is reached.

The M6’s new twin 4km tunnels, connecting Sydney’s south to the wider motorway network, were approved in 2019 and scheduled to open in 2025.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.