Bengaluru: Namma Metro’s driverless train to undergo 37 tests lasting four months

The first set of prototype six coach metro trains, which arrived at Hebbagodi metro depot from China on February 14, is now undergoing multiple tests, according to the Bangalore Metro Rail Corporation Ltd. (BMRCL).

“Being a new rolling stock, multiple tests need to be conducted. Coaches have been assembled before moving to the test track for static and electrical circuits testing. Later, it will be moved to mainline testing,” said BMRCL officials.

Explaining about the tests, Jithendra Jha, project manager, Rolling Stock, BMRCL, said that there are a wide range of about 37 tests which may take four months, followed by system integration with signaling system, telecommunications system, power supply system etc., tests for 45 days. “The statutory safety tests shall include Oscillation Trials by the Research Designs and Standards Organisation (RDSO) and inspection by the Commissioner of Metro Rail Safety (CMRS). Based on the recommendations of RDSO and CMRS, approval of Railway Board to be obtained for introducing the trains for revenue service,” he added.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.