Analytics group signals possible delays at 40% of AI data center construction sites — companies deny schedule holdups, but satellite imagery indicates otherwise

Meta Data center.

Several U.S. data centers slated for completion in 2026 are at risk of being delayed as strict schedules encounter regulatory friction, supply chain bottlenecks, and the lack of available utility. According to a report by the Financial Times, major data center projects involving Microsoft, OpenAI, and other tech companies will miss projected deadlines by more than three months. The estimate is based on data from SynMax, a geospatial data analytics company that uses satellite imaging and AI to deliver real-time insights and predictive analytics on the maritime and energy sectors.

Satellite imagery is used to estimate progress on various construction projects, looking for various milestones like land clearing and foundation work. It’s then cross-checked against industry intelligence, including public statements, regulatory and permit documents, and on-the-ground interviews.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.