Several U.S. data centers slated for completion in 2026 are at risk of being delayed as strict schedules encounter regulatory friction, supply chain bottlenecks, and the lack of available utility. According to a report by the Financial Times, major data center projects involving Microsoft, OpenAI, and other tech companies will miss projected deadlines by more than three months. The estimate is based on data from SynMax, a geospatial data analytics company that uses satellite imaging and AI to deliver real-time insights and predictive analytics on the maritime and energy sectors.
Satellite imagery is used to estimate progress on various construction projects, looking for various milestones like land clearing and foundation work. It’s then cross-checked against industry intelligence, including public statements, regulatory and permit documents, and on-the-ground interviews.