Multiple hurdles are now delaying the rescue of 41 labourers, who have been trapped inside the trapped Silkyara tunnel for two weeks now. With no sign of rescue in the next one or two days, the kin of the trapped workers are getting restless, even as Uttarakhand Chief Minister Pushkar Singh Dhami promised the workers that their safe evacuation was the government’s “top priority”.
For the last 48 hours, there has been no forward movement in the efforts to drill through the tunnel horozontally, as the auger drilling machine stopped working after it reached the 48-metre mark on Thursday, with its blades stuck in the debris, which is full of rock and iron girders. A plasma cutter machine is being brought in from Hyderabad, likely by Sunday, to cut out the stuck auger.