- A project to build a railway bridge in Oxford has cost £237.4m, which is nearly £90m more than the inflation-adjusted cost of the London Eye .
- The final bill significantly exceeded initial estimates of £161m, with construction taking over three and a half years to complete.
- Botley Road has now reopened to reconnect west Oxford with the city centre after years of closure and severe disruption.
- Network Rail apologised for the delays, attributing them to unexpected engineering challenges, including Victorian infrastructure and hidden gas leaks.
- A local campaigner estimated that the prolonged road closure caused local businesses to lose around £50m and resulted in over 120 job losses.
IN FULL
Railway bridge construction project cost more than London Eye and Millennium Bridge