Snowy Hydro 2.0 costs blowout confirmed to be almost $13bn

Snowy 2.0 concrete tunnel liners stored at their production factory
The Snowy Hydro 2.0 project in the Kosciuszko national park location was originally touted by the Turnbull government in 2017 as costing $2bn, and was later revised to $5.9bn. Photograph: Mike Bowers/The Guardian

Snowy Hydro’s two main energy projects have had their completion costs double to almost $13bn as delays and rising costs for equipment and staff take their toll.

The giant Snowy 2.0 pumped hydro project in the Kosciuszko national park, first touted by the Turnbull government in 2017 as costing $2bn, was later revised to a cost of $5.9bn. That tally, though, has escalated to $12bn, with that estimate contingent on completion by the end of 2028.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.