Inbound Kennedy Expressway lanes to fully reopen as first phase of three-year construction project comes to a close

A reopening of the inbound Kennedy Expressway is expected to begin Thursday and continue through Tuesday, when the entire expressway will fully reopen after months of repairs to patch the surface and revamp bridges. (Pat Nabong/Sun-Times)

Motorists weary of crawling for six months through construction on the Kennedy can expect relief in the coming days.

After almost nine months, the entire Kennedy Expressway will fully reopen by Tuesday, according to a news release from the Illinois Department of Transportation.

The reopening comes as the first year of a three-year, $150 million rehab of 7.5 miles of the expressway nears completion. The first phase of the project, which began in March on the heels of the 10-year Jane Byrne Interchange Project, focused on the inbound Kennedy.

Work entailed roadway patching, bridge rehabbing and new lighting, signs and paint between Ohio Street and the junction with the Edens Expressway near Montrose Avenue.

The reopening will take place in phases over the next few days, with overnight lane and ramp closures, IDOT said.

Weather permitting, by 5 a.m. Friday the inbound Kennedy will reopen from Kimball Avenue south. The next phased opening will be at 8 a.m. Saturday when lanes and ramps will fully reopen from Keeler Avenue south. By Tuesday morning, all inbound lanes will be clear just in time for the morning commute, and reversible express lanes will be back to normal.

Drivers will have to bear with some occasional lane closures as the work zone is cleared.

The inbound Kennedy was scheduled to be reduced to one lane Thursday at 8 p.m. between Kimball and Milwaukee avenues, Friday at 8 p.m. between Keeler and Kimball and Monday at 8 p.m. from north of the Edens junction to Keeler Avenue.

Drivers should expect ramp closures in those areas. At midnight Thursday, reversible express lanes will be closed but will reopen Friday. Monday night, reversible express lane entrances at Montrose Avenue will be closed. Drivers can access express lanes at Diversey Avenue.

IDOT will reschedule work if it is delayed because of weather, which could affect lanes reopening.

Construction on the next phase of the project will resume in the spring, focusing on reversible express lanes, IDOT said. Work will get underway on the outbound Kennedy in 2025.

Lanes and ramps on the inbound Kennedy from the Edens to Ohio Street were closed in March for bridge restoration and ramp repairs. Thirty-six bridges were repaired — 22 in the first phase — according to Maria Castaneda, spokesperson for IDOT.

The project aims to improve safety, traffic flow and reliability for the more than 275,000 motorists who use the expressway every day, IDOT said. The Kennedy opened in November 1960, with the last major rehabilitation completed in 1994.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.