A combined length of over 12 km of asphalt surface has been formed as part of the Bengaluru-Chennai Expressway that runs for 105.7-km in State. The four contractors have shown an average progress of around 30% in the ₹5,971.19-crore project. The project is slated to be completed by August 2024.
Official sources in the National Highways Authority of India (NHAI) said that more than 98% of land required for the greenfield project was available. Of the total cost, the amount spent on construction alone would be ₹3,476.54 crore. The height of the road would vary from 3 metres to 5 metres depending on the location.
About 2.5 crore cubic metre of earth would be required for the project. The earth is taken from nearby districts where the departments concerned and respective district administrations were offering support. The contractors need not use fly ash. “If they get the ash, they can use it. It is not mandatory any more,” said a source.