An image of Edinburgh City Council's transport boss is to feature on a new North Bridge mural which is hoped will make ongoing roadworks 'look a lot better'.
It comes just days after the latest estimate revealed repair work to the historic bridge could drag on until 2025 - five years later than originally planned.
In an effort to spruce up the construction site where workers have been carrying out essential repairs since 2018, a huge new mural is set to appear at the south end near to the Royal Mile.
READ MORE: Rotting Edinburgh footbridge over Water of Leith shut over safety fears
The artwork by artist Chris Rutterford, 'Hogmanay at the Tron', depicts crowds enjoying new year's celebrations at the Tron Kirk. Painted over a month at the former parish church in 2013, the piece will make a return to the city centre this week but in a new setting - and with some new faces.
One of them is the city's transport and environment convener Scott Arthur, who said his portrait was added as a thank you for pulling strings within the council to bring the 15-metre mural to the bridge.
Cllr Arthur said: "[Chris] got in touch a couple of weeks ago to say that he's working with businesses on the North Bridge who have been affected by the closure there.
"But there was some bureaucratic hurdles to really make the construction site there look a lot better. I was able to connect him with a few key people inside the council and they got things moving quite quickly.
"As a small thank you for that - and unsolicited I have to say - he's done a little portrait of me on the North Bridge."
Cllr Arthur added he hopes the piece of art can "become a bit of an attraction in its own right".
Last week it was confirmed extensive repairs to the 140 year-old crossing will now not be completed until June 2025 – adding another year to the previous estimate which was already four years behind schedule.
It followed an announcement from the council that restrictions on northbound traffic will be extended into spring 2023.
Cost of the major project rose by £25.7m to £62m earlier this year after it emerged parts of the bridge which had not been inspected since construction in the late 1800s were in need of significant attention and investment.
Cllr Arthur said further investigations uncovered “previously concealed” issues.
He added: “This is an extremely complex project to refurbish Edinburgh’s iconic North Bridge and to ensure its longevity as a key link from the north to the south of the city.
“The historic nature of the project, the age of the structure and its heritage value finds the team uncovering elements of the bridge which require significant specialist work.
“We’re communicating with local residents, businesses and stakeholders, as well as Lothian Buses.”
Sign up to Edinburgh Live's Daily News newsletter to get the latest headlines sent directly to your inbox every day
READ NEXT:
Edinburgh nursery failed to 'respect children's personal space'
BT appeal Edinburgh 'street hub' refusal amid pressure to replace eyesore phone boxes
Edinburgh's only BAME councillor attacks lack of diversity on funding panel
Edinburgh Council owed £11m in rent arrears as more tenants fall into debt
Homelessness rising in Edinburgh amid the cost of living crisis