HS2’s structures should have been ‘largely completed’ by now

HS2’s physical structures should have been ‘largely completed’ by now under the project’s initial timeline but only 60% of the work has been done, MPs were told (Jonathan Brady/PA) - (PA Archive)

HS2’s physical structures should have been “largely completed” by now under the project’s initial timeline but only 60% of the work has been done, MPs were told.

Mark Wild, HS2 Ltd chief executive, said one of the main causes of the delays was starting construction work before designs were finalised and local planning consents were in place.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.