New train services between Newcastle and Northumberland are on track to start next year after the highly-anticipated plans overcame another crucial hurdle.
Construction is due to get underway this summer to restore passenger services to the Northumberland Line, following a critical seal of approval from the government. Six new stations will be built and 18 miles of track upgraded under the proposals to run a half-hourly service between Newcastle and Ashington from December 2023 – stopping at Bedlington, Bebside, Newsham, Seaton Delaval and Northumberland Park.
The project was given a major boost on Monday, as it was confirmed that a Transport and Works Act Order (TWAO) has been granted for it to go ahead, authorising the closure of level crossings, land purchases, and track works. The decision from the transport secretary Grant Shapps comes after a month-long public inquiry last year.