K. Radhakrishnan, Minister for Scheduled Castes and Scheduled Tribes, Backward Classes and Devaswom, has said that the construction of the elephant wall in the Aralam rehabilitation area is expected to be completed ahead of schedule, by June 15.
Initially planned for completion within a year, the project has seen significant progress, with over 2 km of construction already completed. Mr. Radhakrishnan expressed optimism that the accelerated pace could lead to an earlier than anticipated completion. To expedite the process further, additional teams would be deployed.
Acknowledging the necessity of removing trees for the project, he said 67 more trees would be felled in the project area. To monitor the progress of the project, weekly review meetings chaired by the Sub-Collector will be held.