On May 7, 2026, the Supreme Court of India ruled that electricity consumers in Delhi shouldn’t be charged for depreciation costs related to a TATA Power Delhi Distribution plant, as it no longer provides power to the city.
This case involved a disagreement between the Tata Power Delhi Distribution and the Delhi Electricity Regulatory Commission regarding a 108 MW gas-based power plant set up by Tata Power Delhi Distribution Limited (TPDDL) before the 2010 Commonwealth Games to meet the peak electricity demand in the city.