The Hindu Bureau

Suburban rail: Officials directed to complete works related to all four corridors by 2026, says M.B. Patil

Works of Bengaluru Suburban Rail Project (BSRP) corridor-2 between Benniganahalli and Chikkabanavara (25.01 km) will be completed within the set deadline of the next 26 months, while officials have been instructed to work towards completing the works related to all four corridors by 2026, Infrastructure Development Minister M.B. Patil said on Friday. Even if the project gets delayed due to some unforeseen reasons it would be ready by 2028, he added.

He was speaking while reviewing the progress of works along with Minister K.J. George and officials. He began his inspection at Lingarapuram and moved on to Shampura where he reviewed the ongoing railway over-bridge work. Later he visited Hebbal and examined the construction of the station. Finally, he visited Yeshwanthpur where he flagged off the concrete work, according to a release.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.